Project Execution
Highlights:
- Provided the siting, geotechnical investigation, preliminary/detailed engineering, regulatory package, procurement, and construction services required for 2 x 50,000 m3 saline water storage ponds in NE BC
- Collected orthorectified imagery with an Unmanned Aerial Vehicle (UAV), which was used to provide periodic excavation and fill volumes
- Provided onsite QA/QC construction services
- Successful in obtaining approval from BC Regulator
- Implementation of an innovative outtake system
ESG Project Benefits:
- Sustainable water management by promoting produced water recycling and re-use
- Building resilient infrastructure with innovative solutions
- Permanent centralized infrastructure limits trucking and associated air emissions