project details

Inspection of Lime High Density Sludge Treatment System for Dissolved Metals Removal

project overview

Integrated Sustainability completed an inspection of a Mine Water Treatment Plant using a high-density sludge lime treatment to remove dissolved metals. The inspection process reviewed key equipment, operational documentation, and safety measures, supporting the plant’s successful operation.

 

project deliverables

  • Conducted on-site troubleshooting and process optimization over 5 days, including sampling, bench-scale testing, and recommendations for chemical dosing adjustments.
  • Developed of a comprehensive water treatment system optimization plan, assessing operational, economic, and environmental factors, with findings summarized in a technical memo.
  • Supported optimizing instrumentation challenges during the plant start-up phase.
  • Completed project within 2-3 weeks.
  • Supplied long-lead equipment items to site and conducted a site assessment.
  • Developed an execution plan for retrofitting the water treatment plant to operate efficiently at a target throughput of 40 m3/hr.