The Challenge
In order to prevent the client’s pipeline project from being delayed by the winter season, Integrated Sustainability was tasked with obtaining landowner agreements within a six week timeframe. Following this, field investigations had to be completed within three weeks.
The Result
By leveraging local knowledge, staff experience, and effective planning, Integrated Sustainability was able to both obtain landowner permissions and complete field investigations within the allotted timeframes, thereby supporting the regulatory application process.